Under the Party Wall Act a building owner must serve a Notice before starting building works on an
existing party wall or near the boundary.
There is a statutory notice period of two months from the date the Party Wall Notice is served.
During this notice period works cannot start, unless your neighbour agrees to waive this period by
mutual consent.
The notice is only valid for a year, so it is also important that it is not served too early. Planning
permission for the work is not required before issuing a Party Wall Notice.
We always advise building owners to speak to their neighbours before serving a formal notice.
Neighbours that feel they are being consulted and kept informed are far less likely to immediately
appoint a surveyor when a notice is served.